Timeline

PROJECT INITIATED by a committed group of 16 individuals on October 10, 2010.
PRESENTED final plans and estimated costs to the community on October 6, 2013.

APPROVED proposal to start construction by 90.5% majority vote at DMZT Special General Body Meeting on December 8, 2013.

CEREMONIAL GROUNDBREAKING held on March 29, 2014.

CONSTRUCTION STARTED on May 9, 2014.

RAISE the final $1 Million during the 18–month construction period.

COMPLETE construction of the new building by December 2015. Contingency would be to delay non-essential site improvements, amounting to approx. the last $200-300,000.